Sundance NGL Plant II – Pipeline Expansion and Gathering System
Client
Brazos Midstream
Project Year
2024-Present
Project Scope
Final stages of constructing approximately 175 miles of 16-inch through 24-inch high-pressure natural gas gathering pipeline and other associated midstream infrastructure spanning the core of the Midland Basin, including Ector, Howard, Martin, Midland, Glasscock, and Reagan counties. Upon completion of this initial phase of construction, Brazos will operate approximately 260 total miles of natural gas gathering pipelines and 10 compressor stations in the Midland Basin.
Services
- Construction Services
- Pipeline Integrity and Inspection Surveys
- Pipeline Location
- QC/QA (Quality Control/Quality Assurance)
Markets
- Pipeline
CERA Solutions provides construction inspection and field support for the Brazos Midland Basin natural gas gathering pipeline project, covering approximately 175 miles of 16- to 24-inch pipelines and associated compressor stations. Our team monitors pipeline installation, welding, coating, cathodic protection, and pressure testing, with CWI-certified welding inspection and non-destructive examination (AUT/UT) support to verify quality and integrity. CERA oversees QA/QC, safety compliance, and coordination with contractors and Brazos representatives, providing daily logs and detailed reports to ensure compliance, safety, and operational readiness throughout construction.