Texas Gulf Coast Hobson – Fractionation Facility 16” Project
Client
EPIC
Project Year
2019-2020
Project Scope
Construction/Process Management
Services
- Construction Management
- Design
- Master Planning & Site Design
Markets
- Pipeline
Hobson to Robstown was 96 miles of 16” that included three pumpstations and some out station infrastructure work at the point of origin. Our teams worked throughout project design/constructability, ROW acquisition, SOW development, and MOC management. When the project went into construction we performed all construction management, project cost controls, and project coordination duties alongside the client Project Management teams. Once construction activities were complete, we produced the Commissioning & Asset Activation Plans as well as aided in the new asset activation process.